About Project:
Installed all electrical work located within 180 residential units only on 3rd thru 14th floors in a new mixed use 15 story building.
Unusual Challenges: Working on decks during the winter months and the last minute addition of control
wiring required in the decks for the HVAC Contractor.
Creative Solutions: Prefabricated many of the boxes and stub ups prior to installing them in the deck.
Other Noteworthy Facts/Information: Taylor partnered with a larger Electrical Company to complete
approximately 40% of the contract work.
Address/Location:
5105 S. Harper
Customer Name:
JMS Electric, Inc, (GC – Linn-Mathes, Inc)
Project Cost:
$2,548,286.00
Estimated Completion Date:
11/2016
Actual Completion Date:
11/2016
Posted on:
February 13, 2018