City Hyde Park

About Project:

Installed all electrical work located within 180 residential units only on 3rd thru 14th floors in a new mixed use 15 story building.

Unusual Challenges: Working on decks during the winter months and the last minute addition of control
wiring required in the decks for the HVAC Contractor.

Creative Solutions: Prefabricated many of the boxes and stub ups prior to installing them in the deck.

Other Noteworthy Facts/Information: Taylor partnered with a larger Electrical Company to complete
approximately 40% of the contract work.

Address/Location:

5105 S. Harper

Customer Name:

JMS Electric, Inc, (GC – Linn-Mathes, Inc)

Project Cost:

$2,548,286.00

Estimated Completion Date:

11/2016

Actual Completion Date:

11/2016

Posted on:

February 13, 2018